September 2024
The Construction Zone
Crescent School
The old dining hall at Crescent School underwent Type 1, 2, 3 operations for the safe removal of asbestos ahead of demolition, a required government-regulated health & safety practice. As well, electrical and IT services were flagged and hoarding erected as seen in the left photo.
Aurora United Church
With all the exterior walls up and the sheathing in progress at Aurora United Church, installation of the EIFS and roofing is expected to begin this month. On the interior, the balcony seating is awaiting another concrete pour and the steel pan stairs for the South Tower are in production.